§ 744.107. Public utility mains laid before paving.
Latest version.
Prior to the construction, reconstruction or paving of a street, the Public Works
Department shall give notice thereof to utilities and public service companies having
the right to place pipes, mains, ducts, or other facilities, including connections
thereto, under a street. Such utilities or companies shall promptly perform the installation
of new or rehabilitation of existing facilities so as to complete such work prior
to street paving. Except for emergency repair of a failed underground facility, new
street pavement shall not be disturbed by such utilities or companies within five
years following the placing of such pavement.